Piata Universitatii Underground Parking University-Bucharest Project June-August 2011 Daniel BUZILA, MATEIDESZ Gábor HBM SBR / SZIE 2011.11.28.
Pozitie santier Localizare pe harta Locatia cu amplasamentul inainte de demararea proiectului University Square: cu rosu - localizarea santierului pe harta poze cu locatia santierului inainte de excavare statuile au fost mutate si vor fi instalate inapoi dupa finalizarea parcarii
O locatie cu o intreaga istorie Piata Universitatii: Vedere cu zona statuilor 1930-1940 ruinele Manastirii Sf. Sava si Academia Regala Sf, Sava doua cladiri foarte importante din secolul 17 au fost descoperite in inceputul excavatiei; descoperirile arheologice au intarziat demararea proiectului cu aproximativ 6 luni
Informatii despre proiect Subiect: Executie incinta perete mulat Client Final: Square Parking SRL Antreprenor General: Synergy Construct SRL Valoare Proiect: 402 900 EUR Detalii Proiect: Grosime Perete : 60 cm Cota de Fundare: Perimetrul incintei: Termen Finalizare: 20.08.2011-23 m 176.8 m Top-Down area 164 m Struts area
Ajánlatadási szakasz mőszaki érdekességei TU és MMT kidolgozása szereposztás, felelısség Vízzárósági osztálybasorolás osztrák ajánlás
Panelkiosztás kidolgozása SPECIFICATII TEHNICE PE TEHNOLOGIA DETINUTA: PLAN PANOTARE
Résarmatúra terv, betontakarás biztosítása SPECIFICATII TEHNICE PE TEHNOLOGIA DETINUTA : PLAN CARCASE
Munkaterületi organizációs terv PREGATIRE PROIECT PE TEHNOLOGIA DETINUTA Plan Organizare Santier
Közös lónak túros a háta..résvezetı, beton, armatúraszerelés, kirekesztések AGREAT: SCRISOARE DE INTENTIE 37 puncte in scopul antreprenorului General Grinda de Ghidaj Beton Carcase+jontare Macara Etc.
Kivitelezés - Ütemterv
Kivitelezés - Organigram Project manager Contract management with Client Communication with client, designer, suppliers Cost monitoring, controlling Site Engineer Communication with suppliers, subcontractors, designer on SITE Control of execution day /night assistance/ Romanian authorities, safety Quality control Managing, leading the Quality Con. All QC document preparation by QSP and Romanian law Foreman Day Daily execution control Daily costs register Technical sheets filling Site manager Technological control of execution Cost controlling of HBM technology Foreman Night Daily costs register Daily execution control Technical sheets filling Machine operator Worker Kellyman Worker Slurry plant Welder Machine operator Kellyman Slurry plant Mechanic Worker Worker Worker Welder Electrician Mechanic Worker
Kivitelezés kezdeti problémák Megrendelıi szolgáltatások hiánya a tervezett felvonuláskor: VÍZ ÉS ÁRAM ELLÁTÁS TERVEK RÉZSŐVÉDELEM RÉSVEZETİ VÉGLEGES BETON RECEPT ARMATÚRÁK SZERVIZ DARU KÖZMŐ KIVÁLTÁSOK KOMPROMISSZUM.
Kivitelezés - kompromisszum
Kivitelezés felvonulás
Kivitelezés elsı harapások
Kivitelezés a kezdı panel története..
Kivitelezés - organizáció-papír/valóság
Kivitelezés a horog másik végén lenni
Kivitelezés - folytatás
Kivitelezés folytatás, társvállalkozók
Kivitelezés tanulságok BETON
Kivitelezés tanulságok ARMATÚRA ÉS ELHELYEZÉS
Kivitelezés tanulságok SZERVIZ DARU
Kivitelezés tanulságok RÉSVEZETİ
Kivitelezés tanulságok TÁRSVÁLLALKOZÓK ÉS MÁS APRÓSÁGOK AMIVEL NEHÉZ SZÁMOLNI. 7200 PERC-120 ÓRA-5NAP
Stadiu actual, curba perete, panou. si peretele Mulat?