Gazelle Street Improvements 10/4/2018
Brownsville MPO Project Status presentation October 10, 2018
South Port Connector CSJ: 0921 06 288
South Port Connector CSJ: 0921 06 288 Project Limits: From: SH 4 to Ostos Road 1 2 3 4 Typical Section 2 lane Rural Roadway with shoulders ROW Width 1000 feet wide Project Cost $20.1 Million Environmental Status Expected Clearance is January 2019. 5 6 7 ROW Acquisition/Utilities: In Place Available Funding $16.5 Million Design On going, 60% Design plans submitted to TxDOT Distance 2.0 Miles TxDOT Off System Roadway
South Port Connector CSJ: 0921 06 288 Project Limits: From: SH 4 to Ostos Road Complete Environmental Phase December 2018 Finalize USFWS Coordination PROJECT NEEDS Cooperation from TxDOT on Environmental/Design Phases Obtain USACE Corp Permit for impacts to Wetlands Complete Design December 2018 Rider 45 Funding Recommendation October 2018
Veterans International Bridge Fast Lane Project
Veterans International Bridge Fast Lane Project Project Limits: the Veterans Bridge Port of Entry 01 Typical Section 4 12 foot concrete travel lanes 02 ROW/Utilities In place 03 Project Cost $795,000 06 Construction 25% Complete First concrete pour Oct. 10 05 Design Complete 04 Environmental Status Complete Distance 550 feet TxDOT Off System Roadway
Veterans International Bridge Fast Lane Project Project Limits: the Veterans Bridge Port of Entry PROJECT NEEDS 1 2 Start Construction August 27, 2018 Construction Duration 60 Days
Veterans International Bridge Fast Lane Project Project Limits: the Veterans Bridge Port of Entry
Veterans International Bridge Fast Lane Project Project Limits: the Veterans Bridge Port of Entry
Veterans International Bridge BP Primary Lane Expansion
Veterans International Bridge BP Primary Lane Expansion Project Limits: Veterans International Bridge Port of Entry 1 2 3 4 Typical Section Four additional travel lanes ROW/Utilities Complete Project Cost $12 Million Environmental Status Complete 5 6 7 8 Conceptual Planning 100% Complete Technical Requirements Complete Design On going, to be completed Nov. 2018 Funds $6.9 Million CAT 7 Funds In Place Distance 800 feet TxDOT Off System Roadway
Veterans International Bridge BP Primary Lane Expansion Project Limits: Veterans International Bridge Port of Entry PROJECT NEEDS: 01 02 03 Complete Design November 2018 Need to close Funding Gap Cost Benefit Analysis in Progress
SH 550 GAP 2 PROJECT CSJ: 0684 01 068
SH 550 GAP 2 PROJECT CSJ: 0684 01 068 Project Limits: From: 0.203 miles S. of FM 1847 to 1.13 miles S. of UPR Overpass @ FM 3248 1 2 3 4 Typical Section 4 lane tolled expressway with shoulders ROW Width 150 to 400 feet wide Project Cost $16 Million Environmental Status Complete 5 6 7 ROW Acquisition/Utilities Complete Available Funding $16.5 Million Design Update existing plans Distance 2.6 Miles TxDOT Off System Roadway
SH 550 GAP 2 PROJECT CSJ: 0684 01 068 Project Limits: From: 0.203 miles S. of FM 1847 to 1.13 miles S. of UPR overpass @ FM 3248 PROJECT NEEDS: 1 2 3 4 5 Update the design plans to meet interstate standards Need AFA for CAT 7 Funds Need FAA for CAT 12 Funds Complete design plans by June 2019 Negotiate and Approve Work Authorization with Engineering Consultant
OLD ALICE ROAD CSJ: 0921 06 290
OLD ALICE ROAD CSJ: 0921 06 290 Project Limits: From: SH 550 to SH 100 01 02 Typical Section 4 lane Urban Roadway with shoulders ROW/Utilities 120 feet wide 03 Project Cost $12 Million 05 Design Pending (County) 04 Environmental Status In Progress (Categorical Exclusion) Distance 3.5 Miles TxDOT Off System Roadway
OLD ALICE ROAD CSJ: 0921 06 290 Project Limits: From: SH 550 to SH 100 PROJECT NEEDS: 1 2 3 4 5 Complete Environmental Phase Fall 2018 Obtain USACE Corp Permits for impacts to Wetlands Obtain traffic numbers for Noise Analysis Cultural Resources (County) Design (County)
MORRISON ROAD CSJ: 0921 06 291
MORRISON ROAD CSJ: 0921 06 291 Project Limits: From: FM 1847 to FM 511 01 Typical Section 2 lane Rural Roadway with center turning lane 06 Design: Pending 02 ROW/Utilities 120 feet wide 05 ROW Acquisition/Utilities Pending 03 Project Cost To be determined 04 Environmental Status (Environmental Assessment)Pending 4.5 Miles Distance TxDOT Off System Roadway
MORRISON ROAD CSJ: 0921 06 291 Project Limits: From: FM 1847 to FM 511 PROJECT NEEDS: 01 02 03 Begin Environmental and Complete Environmental Phase Fall 2019 Need AFA for CAT 7 Funds Begin USFWS Coordination 04 Negotiate and Approve Work Authorization with Consultant
WHIPPLE ROAD CSJ: 0921 06 292
WHIPPLE ROAD CSJ: 0921 06 292 Project Limits: From: FM 1575 to FM 1847 01 Typical Section 2 lane Rural Roadway with shoulders 02 ROW/Utilities 80 feet wide 03 Project Cost To Be Determined 06 05 04 Design Pending ROW Acquisition/Utilities Pending Environmental Status Pending 1.3 Miles Distance TxDOT Off System Roadway
WHIPPLE ROAD CSJ: 0921 06 292 Project Limits: From: FM 1575 to FM 1847 PROJECT NEEDS: 01 02 03 Begin Environmental Document Need AFA for CAT 7 Funds Negotiate and Approve Work Authorization with Consultant
East Loop
East Loop Project Limits: From: I 69E to SH 4 01 Typical Section 4 lane to 6 lane divided Roadway with shoulders 06 Design Pending 02 ROW/Utilities 120 400 feet wide 05 ROW Acquisition/Utilities Pending 03 Project Cost $60 Million 04 Environmental Status In Progress. Combine both documents in house. 11.2 Miles Distance TxDOT Off System Roadway
East Loop Project Limits: From: I 69E to SH 4 PROJECT NEEDS: 1 2 3 4 5 Need AFA for CAT 7 Funds Negotiate and Approve Work Authorization with Consultant Combine Environmental Documents into one document Complete Schematics to reflect Value Engineering Incorporate Value Engineering into EA
U.S. 77 Conceptual Plan