1. sz. melléklet: Conception plan for the long-term task following the abandonment of uranium ore mining MECSEKÉRC RT., 2001.
|
|
- Dávid Faragó
- 8 évvel ezelőtt
- Látták:
Átírás
1
2 1. sz. melléklet: Conception plan for the long-term task following the abandonment of uranium ore mining MECSEKÉRC RT., 2001.
3 CONCEPTION PLAN FOR THE LONG-TERM TASKS FOLLOWING THE ABANDONMENT OF URANIUM ORE MINING Pécs, January 2002
4 CONCEPTION PLAN FOR THE LONG-TERM TASK FOLLOWING THE ABANDONMENT OF URANIUM ORE MINING Written by: Zsolt Berta head of environmental protection base József Csicsák head of environmental monitoring Supervised by: Approved by: Jenő Bánik technical director István Benkovics director general Pécs, January 2002
5 CONTENTS 1. ANTECEDENTS LEGAL BACKGROUND AUTHORIAL PRESCRIPTIONS DEFINING THE LONG-TERM TASKS SUBSEQUENT CONTROLLING, AFTER-CARE PHASE LONG-TERM CONTROL AND MAINTENANCE GROUPING THE TASKS ACCORDING TO HAZARD POINTS RADIOACTIVITY Areas with unlimited utilization Radon effluence from the abandoned mining cavities Radioactivity of isolated areas with limited utilization Monitoring the radioactive emissions Radiation protection control DAMAGE DUE TO MINING OPERATION SURFACE AND GROUNDWATER CONTAMINATION Areas with unlimited utilization Abandoned mine openings Areas with limited utilization Water decontamination systems Maintenance of hydraulic engineering structures CONDITION SYSTEM FOR COMPLETING THE TASKS ENVIRONMENTAL MONITORING Field measuring, sampling and data recording activity Laboratory analysis activities Data processing, interpreting and modeling activities Informing the authorities and the public ENVIRONMENTAL PROTECTION OPERATION Uranium removal from the surface and groundwaters Desalinization of groundwaters Maintaining the water purifying plants, the decontamination and drainage systems Maintenance and after-care of areas with limited utilization DRAFT DATA REGARDING THE AMOUNT OF LONG-TERM TASKS... 19
6 1 1. Antecedents The Government made a decision in its decree No. 2085/1997 (IV. 3.) on the termination of the unprofitable uranium ore mining in the Mecsek Mts. in 1997, and on the completion of mine closure, reclamation and environmental protection tasks till The Government decision No. 2385/1997. (XI. 26.) approved the Investment Program regarding the performing of uncompleted tasks in connection with the remediation of environmental damages caused by the uranium ore mining and milling, the remediation of environment and the abandonment of activities. From the Government, the predecessor of the Ministry of Economy, the IKIM became to be responsible for the investment, while the predecessor of the MECSEKÉRC Inc., the Mecsek Ore Mining Co. (MÉV) has become the investor. The investment has started on 1 st of January 1998, according to the plans. The time schedule of remediation of the tailing ponds had to be modified because of additional technological reasons having emerged meantime, therefore the Government changed with its decision No. 2006/2001. (I. 17.) the final completion date of the Program as 2004, having left the investment costs unchanged. The Investment Program (from this point: IP) was made based on the study titled Conception plan for the entire abandonment of the uranium ore mining in the Mecsek Mts. approved by the authorities, and its carrying out was approved by the Government in a decision. The remediation works defined in the IP have started from January 1998, while the Environmental Protection License (from this point: EPL) needed for the abandonment of uranium industry according to the concerning law was approved only in November 1998, therefore the IP wasn t able to take into account all obligations prescribed in the EPL. However, the Conception Plan being the basis of the IP has already defined subsequent maintenance jobs and long-term operational, maintenance tasks, and has contained cost plans for these tasks, but the direct plans of the financing of these tasks weren t able to be determined in the IP, because of the lack of authorial prescriptions and of remediation experiences. To solve this problem, the Government in its 2006/2001. (I. 17.) decision charged the Ministry of Economy with the elaboration of the financing of long-term tasks from This paper was made to define the long-term controlling, maintenance and operational tasks Legal background Authorial prescriptions The environmental protection requirement system of the abandonment of uranium ore mining was determined by the Environmental Protection License (EPL) issued by the South Transdanubian Environmental Protection Inspectorate under the number /1998. The section 2.2. of the EPL deals with the defining of the tasks following the completion of the Investment Program, then in Chapter II there are direct prescriptions regarding the fulfillment of long-term tasks following the term of IP. In the following part
7 2 the more important authorial prescriptions of general character concerning the long-term tasks are discussed. The direct prescriptions are discussed at the enumeration of objects. Prescriptions written in the environmental protection license No /1998. by the South Transdanubian Environmental Protection Inspectorate. I.2.2. Tasks and operation after 2002 In 2002 the activities of construction character planned in connection with the abandonment of uranium ore mining will be finished. The remediation activities will continue for a time period currently can be estimated with uncertainty, as a part of reclamation, the restoring of conditions of some environmental elements will continue for decades or centuries. Some of the remediated facilities can t be abandoned, keeping them in a required condition is also a long-term task I Monitoring Hydrogeological monitoring Its operation is expected to last for several decades, the professional tasks are nearly the same than in the previous period. Planned study programs: Immediately after remediation a detailed controlling and qualification program, which is the zero conditions assessment at one site, the process of declaration to be remediated at another site. Carrying out systematic measurements, tests by the order corresponding the expectable effects. Revision of monitoring system in every five years, evaluation, planning. Radiological monitoring The system is expected to be needed for 10 years after 2002 with less requirements and capacity. Planned studies: Detailed controlling and qualification program after completing remediation works of an object, which is the zero conditions assessment at one site, the process of declaration to be remediated at another object. On the reclaimed waste rock piles and in their surroundings, the radioactive element content of soil and plants, the gamma-dose rate in air and the radon exhalation is tested quarterly. Rock movement monitoring The existing subsystems of monitoring are suitable for this task. The surface measurement network is planned to be established I Water treatment The limited extent and controlled drain of area affected by mining is needed for long time to prevent the spreading of unfavorable effects. The water quality after the water filling predicted to last for 33 years can be estimated hardly. The mine water pumping is a long-term task.
8 3 The time period of remediation in connection with tailing ponds, the finishing of water pumping is also expected to be long-term. It is necessary to take care of the treatment of pumped water for achieving defined limits, as condition of leading it into the recipient. The operation of water treatment plant involves tasks of waste disposal I Maintenance In the course of remediation, the using of technical methods requiring the less maintenance has been a principle. After the entire completion of remediation (finished mine water pumping, finished decontamination, finished water clarifying), there will be further tasks to keep the constructed structures in required conditions and controlling them by operating and maintaining: the cover layer, the vegetation, the water drainage system, and the monitoring networks. II.1. General liabilities associated with the activity In the course of activity the tasks has to be completed, in the defined way and at the defined degree. The investments that dragged on or failed, the maintenance, operational and monitoring activities related to the completed remediation works and their long-term development requirements have to be taken into overall consideration. The organization, personal and economical conditions needed for performing the remaining tasks should be developed. 2. Defining the long-term tasks For the long-term successfulness of technical interventions of reclamation and environmental protection purposes carried out according to the plans of IP and according to the authorial prescriptions controlling, monitoring and maintenance tasks should be performed that are of different degree, character and term for each objects. These tasks are divided into two phases depending on the amount and character of the required activities and according to the methodology accepted internationally in the remediation practice: The first phase of 5 years, which contains generally wider and more diverse control and more intensive after-care, while the second long-term phase requires only limited control and after-care as needed.
9 Subsequent controlling, after-care phase The first phase representing practically an about 5-years long term after the completion of the remediation works of each objects requires considerable amount of controlling, monitoring and after-care activities. This term requires a more frequent and rigorous control in space and time as well, and considering the studied parameters, too. Its purpose is to verify the long-term stability and efficiency of the remediated environment and the completed technical interventions, to justify the fulfillment of the prescribed limit values, to carry out the needed maintenance interventions for the keeping the efficiency of constructed facilities (rainfall water discharging systems, cover layers, vegetation cover for the protection against erosion, etc.), and to repair these facilities, restoring their original conditions. In this phase biological monitoring is required to observe the conditions of the completed planting, which one directs the replacements and corrections taking into account the soil forming and the features of the biotope. In the course of biotope development, the selfsustaining system forms in this phase, ensuring the protection against the erosion. The repairing of eroded areas forming as consequence of the planting failed to come about or of other causes, the configuration of the needed maintenance and operation system of hydraulics engineering structures for the discharging rainfall. The optimization based on modeling of water damage preventing systems planned for long-term operation, the development of technologies in such a way that makes the cost reduction and the accordance with the new norms of the European Union possible should be completed in this phase. In the field of uranium removal, especially around the waste rock piles, the discovery of possibilities of using passive, low-cost natural technologies. In this phase the expected time, cost and technology requirements of interventions should be refined, by the help of the intensive monitoring data analyses. The elements of the long-term required monitoring system, the frequency of control, the order of maintenance and operation should be determined till the end of the after-care period Long-term control and maintenance The second phase contains the environmental monitoring and maintenance tasks of the remediated objects as needed, and its term can be determined on the basis of examination performed periodically (in every 5 years according to the Environmental Protection License), however, it is evident just now, that these activities will have to be continued after years around some objects (e.g. abandoned mining cavities, tailing ponds). In the long-term phase the operational and maintenance activities will go on in the remediation systems, the northern mine plants will be filled with water in this period, the uranium removal from the mine waters will have to be continued. The engineering structures constructed in the course of remediation activities will have to be inspected, the maintenance works of needed extent will have to be carried out.
10 5 The composition, frequency and denseness of inspections can be developed according to the experiences of the subsequent monitoring phase. Considerable part or in optimal case the majority of the elements studied systematically till that time can be omitted, but the adequately isolated, radioactively contaminated material cannot get into the environment even in the future, too, therefore it will have to be re-examined systematically. The analysis of such sensitive parameters should be preferred, that predict the possible environment pollution in advance, so the intervention can be carried out in time. The southern phase of water remediation for the removal of salt contamination can be finished in this stage. The filling of the mine cavities of the northern region may require the intensification of uranium removal as well. The informing the authorities and the public will serve for the so-called reminding in this phase. The protection of objects that cannot be disturbed should become a community task. 3. Grouping the tasks according to hazard points Finishing the Investment Program such hazard points have still remained that require control and gradual elimination. After finishing the mining all the factors should be taken into account that verify the operation of monitoring systems. The following grouping lists the main hazard points according to the origin of contamination. The factors are discussed subordinated to them, that endanger the final results of completed works and remediated objects (erosion, desiccation, plant decease, etc.) Radioactivity Areas with unlimited utilization Principally all contaminations were removed from the areas with unlimited utilization, and this had to be verified with detailed survey including the analyses of every contaminants after the remediation. The authority issues the declaration on the inactivity based on this survey and on its own controlling analyses. However, such contaminations can remain (because of the character of the radioactive polluting material) that have remained unknown even after a very circumspectly accomplished survey, and perhaps they can be mobilized in the future (it should be presumed primarily in the case of groundwaters, but the remaining of small contaminated soil spots also cannot be excluded without doubt). The measurements of subsequent control: Gamma dose rate measurements. Air 222 Rn concentration and soil surface 222 Rn exhalation measurements. Soil and plant sampling, determination of the specific radioactivity and radionuclide composition of samples.
11 6 The control should cover the 5 years long subsequent control period only; if no contamination is found during this period, the problem can be finally closed with the winding up of the possibly revealed contaminations. Where planting is prescribed in the licenses, proposal for the possible replacement can be made for the new users or owners according to the measurement results of the biological monitoring Radon effluence from the abandoned mining cavities Above the abandoned mining cavities because of tectonic and loosening originated fractures extra radon effluence is expected, primarily on those areas, where both the cavity system and the ore-bearing layer is situated close to the surface (max. several 100 m depth). Such situation can be found on the area of the former Mine Plants #I and #III. Additionally, they affect working and residential areas as well (Kővágószőlős). The following analyses have to be performed on these sites: Soil gas 222 Rn concentration and soil surface 222 Rn exhalation measurements. Integral radon measurements in open place, working and residential environment with SSNTD detectors (solid state trace detectors). Continuous radon monitoring of closed mine cavities (Northern Adit, open shaft of Mine Plant #I). The interventions and radon removal should be carried out depending on the rate of revealed radon effluence, the developed radon concentration and the legal prescriptions expectedly becoming stricter from Radioactivity of isolated areas with limited utilization On these areas the isolation from the environment was made in such a degree, that the authorial prescribed limit values will be kept of great surety. In the subsequent control phase the stability of this isolation should be studied. Subsequently, in favor case, the denseness of monitoring can be lowered radically, but cannot be terminated because of the potential hazard situations discussed in the introduction. In addition, the objects with low radioactive contamination (small waste rock piles, heap leaching areas) should be distinguished from the radioactively strongly contaminated tailing ponds and the Waste Rock Pile #III transformed into central waste disposal facility. The monitoring to be carried out is as follows: Visual inspection of possible damages, alterations. Gamma dose rate measurements. Air 222 Rn concentration and soil surface 222 Rn exhalation measurements. Soil and plant sampling, determination of specific radioactivity and radionuclide composition of samples through gamma-spectrometric method. Study of migration of radioactive elements (vertically in the cover). Study of migration of radioactive elements (horizontally into the environment). The results of samples should be compared with samples coming from geologically-pedologically similar environment, which is free from the industrial activity (background).
12 7 In the surroundings of the tailing ponds and the Waste Rock Pile #III: integral radon measurement with SSNTD technique, and with fix installed monitoring stations. Biological monitoring study of the planted vegetation and the developing biotope. Inspecting the stability and water balance of cover layers with geophysical methods (can it fulfill its task to isolate radioactivity and to reduce infiltration). As a result of the various monitoring, considerable maintenance, repair and function keeping work should be taken into account in this topic. At the end of the 5 years long after-care period, through the evaluation of measurement results a forecast should be made on the successfulness of isolation, the necessity of possible interventions for the selfsustaining Monitoring the radioactive emissions Emission of radioactive materials will occur in the long term period as well (air, waters, wastes, utilizable materials, etc.), which is regulated by the 15/2001. (VI. 6.) KöM (Ministry of Environmental Protection) decree. The monitoring activities for these emissions will have to be continued till the end of the emissions. Gas effluent Radioactive gas effluent is released practically only from the technological system of mine water purification. Elements of effluent monitoring: meteorological station (provides data for the modeling the contamination spreading), continuous aerosol sampling, the determination of natural uranium (U nat ) release into air is based on the measurement of long-life alpha radioactivity of samples. Liquid effluent The sole-point water discharge (into the stream Pécsi-víz) after the purification is controlled continuously. Its monitoring elements and regularity is discussed in chapter 3.3. The radioactive element, U nat and 226 Ra content of effluent should be monitored continuously. Solid waste disposal The remnants of chemical water treatment, the desalinization, and the technological wastes of mine water treatment will are placed into the waste disposal constructed on the Waste Rock Pile #III. Systematic analysis of radioactive element content. Purposeful monitoring the environs of the disposal.
13 Radiation protection control Considerable part of work sites with radiation hazard will cease finishing the remediation activities. However, several work sites and jobs will remain of radiation hazard: the radiation protection monitoring will have to be continued till the end of these activities, according to the current 16/2000. (VI. 8.) EüM (Ministry of Health) decree Damage due to mining operation After the abandonment of mining activities the shafts have been backfilled. Land movements are expected because of the filling of cavities by water, the termination of previous, long-lasting depression and the own processes of cavity system. According to the decision No. 4954/2000/3. by the District Office of the Mining Bureau of Hungary, the following land movement monitoring has to be in operation in the first 5 years, to delete the mining plot and to know the re-utilization accurately: Leveling network (121 reference points). Highly sensitive 3D deformation measurement (on 14 points). GPS network (10 reference points). Systematic inspection of the level of shaft backfilling. In the long-term phase, this system will be winded up gradually according to the possibility for exemption. Intervention is expected only at the backfilling of shafts, and at the maintenance of engineering structures and monitoring elements. Tasks are the operation, the continuous interpretation, modeling and informing as needed, the developing and archiving databases Surface and groundwater contamination The remediation aims and works of the uranium ore mining in the Mecsek Mts. were strongly influenced by the hydrogeological position of the mining area. The aquifer formations of underground mining in the Western Mecsek Mts. are in connection with aquifer formations of drinking water resources both on the north and the south. E.g. the tailing ponds are situated between the drinking water reserves of Tortyogó and Pellérd, on the surface of the aquifer formations of the two reserves, the contamination leaving them endangers directly the aquifer formations of water reserves. To ensure the long-term protection of potable water reserves such facilities were constructed in the course of Investment Program, that are targeted to prevent the contamination of surface and groundwaters, and to treat the already contaminated waters. The maintenance and long-term operation of these decontamination systems will provide the prevention of water pollution, which can be verified through systematic monitoring Areas with unlimited utilization On areas with unlimited utilization since all contaminants as well as the contaminated soil were removed from here only subsequent inspection tasks of limited period
14 9 (generally five years) should be performed, according to authorial prescriptions. Such areas are e.g. the Heap Leaching Pile #I, the territory of the Ore Mill Plant, where the successfulness of remediation should be verified through measurement time series in existing shallow groundwater monitoring boreholes Abandoned mine openings In the course of uranium ore mining underground cavities of approximately 18 million m 3 volume were produced. Their most part (cavity systems of Mine Plants #I-#II-#III-#IV) forms a contiguous and interconnected cavity system, while the underground areas of Mine Plant #I represent an independent cavity system. After abandonment the cavity system fills up with water, which leaches contaminants from the loosened rocks in concentration above the limit values, as a consequence of the altered geochemical conditions due to mining activities. The contaminated waters can migrate from the filled cavities left to themselves, therefore other aquifer formations can be contaminated. Accordingly, the abandonment had to be done in planned way, ensuring that the mine waters come to the surface on a single point. Other situation can be found in the Mine Plant #I, where the entire filling up cannot be allowed for the time while the water in the cavity system contains dissolved uranium above the limit value, since it endangers the water reserves of Tortyogó and Pellérd. A depression of almost 100 m should be maintained in the cavity system till the adequate water quality will be achieved. The control of filling up and the treatment of contaminated water filling the cavity systems will require both monitoring and operational tasks in long-term. Concerning prescriptions: 6 th, 7 th, 8 th, 11 th and 12 th paragraphs of EPL II.3.1. point Monitoring The monitoring is a long-term task in the case of mine cavities, considering the slow process of filling up. Therefore the followings have to be monitored long-term: The process of filling up of mine cavities should be controlled on monitoring points installed in the period of IP. It takes approximately years, according to the current studies. The depression developed in the course of mining, its change during the filling up should be monitored for the prediction of communication towards other aquifer formations. Monitoring system should be maintained and operated to control the water quality of various aquifers around the objects. The depression effect of water pumping in the Mine Plant #I should be monitored, to keep the water reserves of Tortyogó and Pellérd secure. It should be verified, that the adequate protection exists around the Waste Rock Piles #I and #III, as a result of this depression.
15 10 During the filling up, the quality of cavity filling water has to be controlled systematically through analyzing different components (radioactive elements, heavy and toxic metals, hydrocarbons) Mine water treatment After finishing the uranium ore mining, waters with high uranium content should be expected for a long period, that have to be the uranium removed from. Expectedly 3-4 t/year in the first period, and later 2-3 t/year uranium will have to be extracted from the water. The depression effect of Mine Plant #I should be ensured for a long period in a way that meets the requirements (keeping the water level prescribed for mine cavities), from the originating water of high uranium content the uranium has to be removed, the controlled water direction and the transformation of uranium extracted from water into manageable form have to be ensured. After the northern mine plants will fill up that is expected to happen in about years the uranium removal from the mine water discharged through the Northern Adit highly probably will be necessary. Pumping and treating the water of high uranium content from the Mine Plant #I For the protection of the water reserves of Tortyogó-Pellérd, the water level in the cavities of Mine Plant #I the water level should be kept at about 100 m depth from the surface. The uranium should be removed from pumped water after pumped out. Regarding prescriptions: Water operation license of the DDVIZIG (South Transdanubian Water Authority) No. 6236/ EPL of DDKÖFE (South Transdanubian Environmental Protection Inspectorate), No /1998., 12 th paragraph of point 3.1., 1 st paragraph of point The depression effect of Mine Plant #I should be ensured for a long period in a way that meets the requirements (keeping the water level prescribed for mine cavities). The water level in the cavities has to be kept on the +65 m a.s.l. From the pumped out water of high dissolved uranium content the uranium has to be removed adequately, the controlled water direction and the transformation of uranium extracted from water into final product of peroxide form have to be ensured. The single-point discharge of treated water into the surface recipient has to be provided. The quality of pumped and treated water, and the efficiency of treatment technology should be monitored. Treatment of waters from the northern mine plants It is expected that the dissolved uranium content of water will increase in the future, after the mine cavities will filled up (Water protection plan of the abandonment of uranium ore mining in the Mecsek Mts., BKMI Ltd. 1998), and the water will get to the surface as free outflow through the Northern Adit. The uranium should be removed from this water, too, its volume is expected to be about 500,000 m 3 /year.
16 11 The removal of uranium from the waters of Mine Plant #III, their analysis, fitting the discharge system into the control technique system, as needed. Forecasting the appearance of springing waters, monitoring the temporal changes of water quality Areas with limited utilization Those areas belong to the group of areas with limited utilization that contain polluting or contaminated materials, waste rock, tailings or contaminated soil, which represents potential for surface and groundwater contamination. On these areas the spreading of contamination is prevented by some kind of isolating layer (cover) in the way that it reduces the infiltration of precipitation water, thus the leaching of polluting materials as well. Amongst the areas with limited utilization mainly the tailing ponds will require long-term monitoring and maintenance activities, considering that the cover layer placed in the course of remediation plays important role in the prevention of infiltration of surface waters. In addition, the waters springing from below the waste rock piles represent important hazard points for the surface and groundwaters of the environment, since they have surely high dissolved uranium and possibly other heavy metal content. In the period of subsequent control phase the integrity of cover layers and the result of planting should be checked visually, the quality of water springing from below and flowing away from the objects should be monitored, monitoring system should be maintained and operated to control the quality of groundwaters in the surroundings of objects, around the waste rock piles primarily considering the radioactive elements and toxic heavy metals, while around the tailing ponds monitoring primarily the dissolved inorganic salts, the stability and protection efficiency of engineering interventions accomplished in the course of remediation should be verified through measurements, increased maintenance activity should be performed to keep the isolation capability of the cover layer, for the development of self-sustaining ability of the planted vegetation and plant associations, the replacement of plants and the promotion of appropriate vegetating should be done as necessary (e.g. systematic mowing), the emerging erosion damages have to be repaired, the waters of high dissolved uranium content springing from below the waste rock piles (Waste Rock Piles #I, #II, #III) have to be collected and diverted into the cavities of Mine Plant #I or into the Mine Water Treatment Plant for treatment. In the long-term period reduced monitoring activity of the quality of surface and groundwaters should be performed, maintenance tasks should be fulfilled periodically, as needed,
Extreme flood events in the Lower Tisza Region The relevance of the excess water
Extreme flood events in the Lower Tisza Region The relevance of the excess water Dr. Péter Kozák Ph.D Director Flooded areas in Hungary before the beginning of river regulation works (1846.) Temporary
RészletesebbenA modern e-learning lehetőségei a tűzoltók oktatásának fejlesztésében. Dicse Jenő üzletfejlesztési igazgató
A modern e-learning lehetőségei a tűzoltók oktatásának fejlesztésében Dicse Jenő üzletfejlesztési igazgató How to apply modern e-learning to improve the training of firefighters Jenő Dicse Director of
RészletesebbenExpansion of Red Deer and afforestation in Hungary
Expansion of Red Deer and afforestation in Hungary László Szemethy, Róbert Lehoczki, Krisztián Katona, Norbert Bleier, Sándor Csányi www.vmi.szie.hu Background and importance large herbivores are overpopulated
RészletesebbenUsing the CW-Net in a user defined IP network
Using the CW-Net in a user defined IP network Data transmission and device control through IP platform CW-Net Basically, CableWorld's CW-Net operates in the 10.123.13.xxx IP address range. User Defined
RészletesebbenEN United in diversity EN A8-0206/445. Amendment
21.3.2019 A8-0206/445 445 Title Proposal for a DIRECTIVE OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL amending Directive 2006/22/EC as regards enforcement requirements and laying down specific rules with
RészletesebbenEN United in diversity EN A8-0206/419. Amendment
22.3.2019 A8-0206/419 419 Article 2 paragraph 4 point a point i (i) the identity of the road transport operator; (i) the identity of the road transport operator by means of its intra-community tax identification
RészletesebbenSTUDENT LOGBOOK. 1 week general practice course for the 6 th year medical students SEMMELWEIS EGYETEM. Name of the student:
STUDENT LOGBOOK 1 week general practice course for the 6 th year medical students Name of the student: Dates of the practice course: Name of the tutor: Address of the family practice: Tel: Please read
RészletesebbenSAJTÓKÖZLEMÉNY Budapest 2011. július 13.
SAJTÓKÖZLEMÉNY Budapest 2011. július 13. A MinDig TV a legdinamikusabban bıvülı televíziós szolgáltatás Magyarországon 2011 elsı öt hónapjában - A MinDig TV Extra a vezeték nélküli digitális televíziós
RészletesebbenConstruction of a cube given with its centre and a sideline
Transformation of a plane of projection Construction of a cube given with its centre and a sideline Exercise. Given the center O and a sideline e of a cube, where e is a vertical line. Construct the projections
RészletesebbenDecision where Process Based OpRisk Management. made the difference. Norbert Kozma Head of Operational Risk Control. Erste Bank Hungary
Decision where Process Based OpRisk Management made the difference Norbert Kozma Head of Operational Risk Control Erste Bank Hungary About Erste Group 2010. 09. 30. 2 Erste Bank Hungary Erste Group entered
Részletesebben2. Local communities involved in landscape architecture in Óbuda
Év Tájépítésze pályázat - Wallner Krisztina 2. Közösségi tervezés Óbudán Óbuda jelmondata: Közösséget építünk, ennek megfelelően a formálódó helyi közösségeket bevonva fejlesztik a közterületeket. Békásmegyer-Ófaluban
RészletesebbenDG(SANCO)/2012-6290-MR
1 Ensure official controls of food contaminants across the whole food chain in order to monitor the compliance with the requirements of Regulation (EC) No 1881/2006 in all food establishments, including
RészletesebbenUtasítások. Üzembe helyezés
HASZNÁLATI ÚTMUTATÓ Üzembe helyezés Utasítások Windows XP / Vista / Windows 7 / Windows 8 rendszerben történő telepítéshez 1 Töltse le az AORUS makróalkalmazás telepítőjét az AORUS hivatalos webhelyéről.
RészletesebbenFAMILY STRUCTURES THROUGH THE LIFE CYCLE
FAMILY STRUCTURES THROUGH THE LIFE CYCLE István Harcsa Judit Monostori A magyar társadalom 2012-ben: trendek és perspektívák EU összehasonlításban Budapest, 2012 november 22-23 Introduction Factors which
RészletesebbenUSER MANUAL Guest user
USER MANUAL Guest user 1 Welcome in Kutatótér (Researchroom) Top menu 1. Click on it and the left side menu will pop up 2. With the slider you can make left side menu visible 3. Font side: enlarging font
RészletesebbenEN United in diversity EN A8-0206/482. Amendment
21.3.2019 A8-0206/482 482 Recital 13 g (new) (13g) In recognition of the need for specific treatment for the transport sector, in which movement is the very essence of the work undertaken by drivers, the
RészletesebbenBaldwin St S Ashburn Rd Baldwin St N Anderson St Thickson Rd N Exhibit 'A' to Amendment to the Whitby Official Plan Exhibit 1 Deferral #2 Modification
Baldwin St S Ashburn Rd Baldwin St N Anderson St Thickson Rd N Exhibit 'A' to Amendment to the Whitby Official Plan Exhibit 1 Modification #3 Brawley Rd W Brawley Rd E U Add: Community Central Area Add:
RészletesebbenCorrelation & Linear Regression in SPSS
Petra Petrovics Correlation & Linear Regression in SPSS 4 th seminar Types of dependence association between two nominal data mixed between a nominal and a ratio data correlation among ratio data Correlation
RészletesebbenFÖLDRAJZ ANGOL NYELVEN
Földrajz angol nyelven középszint 1411 ÉRETTSÉGI VIZSGA 2015. május 14. FÖLDRAJZ ANGOL NYELVEN KÖZÉPSZINTŰ ÍRÁSBELI ÉRETTSÉGI VIZSGA JAVÍTÁSI-ÉRTÉKELÉSI ÚTMUTATÓ EMBERI ERŐFORRÁSOK MINISZTÉRIUMA Paper
RészletesebbenCashback 2015 Deposit Promotion teljes szabályzat
Cashback 2015 Deposit Promotion teljes szabályzat 1. Definitions 1. Definíciók: a) Account Client s trading account or any other accounts and/or registers maintained for Számla Az ügyfél kereskedési számlája
RészletesebbenMagyar ügyek az Európai Unió Bírósága előtt Hungarian cases before the European Court of Justice
Magyar ügyek az Európai Unió Bírósága előtt Hungarian cases before the European Court of Justice FEHÉR Miklós Zoltán Közigazgatási és Igazságügyi Minisztérium Európai Uniós Jogi Főosztály Ministry of Public
RészletesebbenA rosszindulatú daganatos halálozás változása 1975 és 2001 között Magyarországon
A rosszindulatú daganatos halálozás változása és között Eredeti közlemény Gaudi István 1,2, Kásler Miklós 2 1 MTA Számítástechnikai és Automatizálási Kutató Intézete, Budapest 2 Országos Onkológiai Intézet,
RészletesebbenEEA, Eionet and Country visits. Bernt Röndell - SES
EEA, Eionet and Country visits Bernt Röndell - SES Európai Környezetvédelmi Ügynökség Küldetésünk Annak elősegítése, hogy az EU és a tagállamok a szükséges információk alapján hozhassák meg a környezet
RészletesebbenEN United in diversity EN A8-0206/473. Amendment
21.3.2019 A8-0206/473 473 Recital 12 d (new) (12d) Since there is no sufficient link of a driver with a territory of a Member State of transit, transit operations should not be considered as posting situations.
RészletesebbenNSR Settlements. This session will discuss:
NSR Settlements NSR Settlements This session will discuss: purpose and meaning of settlement agreements and the types of settlement agreements relationship between Consent Decrees and Title V applicable
Részletesebbenépítészet & design ipari alkalmazás teherautó felépítmény
A Design-Composit egy kompozitpaneleket gyártó vállalat, mely teherautó felépítményekhez, az építészet számára és design termékekhez készít paneleket. We are an innovative manufacturer of composite panels
Részletesebbenó Ú ő ó ó ó ö ó ó ő ö ó ö ö ő ö ó ö ö ö ö ó ó ó ó ó ö ó ó ó ó Ú ö ö ó ó Ú ú ó ó ö ó Ű ő ó ó ó ő ó ó ó ó ö ó ó ó ö ő ö ó ó ó Ú ó ó ö ó ö ó ö ő ó ó ó ó Ú ö ö ő ő ó ó ö ö ó ö ó ó ó ö ö ő ö Ú ó ó ó ü ú ú ű
RészletesebbenSkills Development at the National University of Public Service
Skills Development at the National University of Public Service Presented by Ágnes Jenei National University of Public Service Faculty of Public Administration Public Ethics and Communication 13. 12. 2013
RészletesebbenProfessional competence, autonomy and their effects
ENIRDELM 2014, Vantaa Professional competence, autonomy and their effects Mária Szabó szabo.maria@ofi.hu www.of.hu The aim and the planned activities at this workshop Aim: To take a European survey on
RészletesebbenMiskolci Egyetem Gazdaságtudományi Kar Üzleti Információgazdálkodási és Módszertani Intézet Factor Analysis
Factor Analysis Factor analysis is a multiple statistical method, which analyzes the correlation relation between data, and it is for data reduction, dimension reduction and to explore the structure. Aim
RészletesebbenÉv Tájépítésze pályázat Wallner Krisztina. 1. Vízparti sétány kiépítése Balatonfüreden, 3 km hosszon
Év Tájépítésze pályázat Wallner Krisztina 1. Vízparti sétány kiépítése Balatonfüreden, 3 km hosszon A következetes városrehabilitáció során Balatonfüred fürdő-városrészében, 2006-2015 között terveink alapján
RészletesebbenFelnőttképzés Európában
Felnőttképzés Európában Nincs szükség annyi diplomásra, amennyit képeznek Helyettük szakképzett emberekre lenne kereslet Az itthon OKJ-s képzés európai hagyományában két vonal érvényesül: - dán - német
RészletesebbenBKI13ATEX0030/1 EK-Típus Vizsgálati Tanúsítvány/ EC-Type Examination Certificate 1. kiegészítés / Amendment 1 MSZ EN 60079-31:2014
(1) EK-TípusVizsgálati Tanúsítvány (2) A potenciálisan robbanásveszélyes környezetben történő alkalmazásra szánt berendezések, védelmi rendszerek 94/9/EK Direktíva / Equipment or Protective Systems Intended
RészletesebbenStatistical Inference
Petra Petrovics Statistical Inference 1 st lecture Descriptive Statistics Inferential - it is concerned only with collecting and describing data Population - it is used when tentative conclusions about
RészletesebbenSebastián Sáez Senior Trade Economist INTERNATIONAL TRADE DEPARTMENT WORLD BANK
Sebastián Sáez Senior Trade Economist INTERNATIONAL TRADE DEPARTMENT WORLD BANK Despite enormous challenges many developing countries are service exporters Besides traditional activities such as tourism;
RészletesebbenGeneral information for the participants of the GTG Budapest, 2017 meeting
General information for the participants of the GTG Budapest, 2017 meeting Currency is Hungarian Forint (HUF). 1 EUR 310 HUF, 1000 HUF 3.20 EUR. Climate is continental, which means cold and dry in February
RészletesebbenContact us Toll free (800) fax (800)
Table of Contents Thank you for purchasing our product, your business is greatly appreciated. If you have any questions, comments, or concerns with the product you received please contact the factory.
RészletesebbenImplementation of water quality monitoring
Joint Ipoly/Ipel Catchment Management HUSK/1101/2.1.1/0153 Implementation of water quality monitoring Dr. Adrienne Clement clement@vkkt.bme.hu Budapest University of Technology and Economics Department
RészletesebbenCONCERTO COMMUNITIES IN EU DEALING WITH OPTIMAL THERMAL AND ELECTRICAL EFFICIENCY OF BUILDINGS AND DISTRICTS, BASED ON MICROGRIDS. WP 5 Del 5.
CONCERTO COMMUNITIES IN EU DEALING WITH OPTIMAL THERMAL AND ELECTRICAL EFFICIENCY OF BUILDINGS AND DISTRICTS, BASED ON MICROGRIDS WP 5 Del 5.14 1 st period Szentendre Papers and articles in specialist
Részletesebben7 th Iron Smelting Symposium 2010, Holland
7 th Iron Smelting Symposium 2010, Holland Október 13-17 között került megrendezésre a Hollandiai Alphen aan den Rijn városában található Archeon Skanzenben a 7. Vasolvasztó Szimpózium. Az öt napos rendezvényen
RészletesebbenBird species status and trends reporting format for the period (Annex 2)
1. Species Information 1.1 Member State Hungary 1.2.2 Natura 2000 code A634-B 1.3 Species name Ardea purpurea purpurea 1.3.1 Sub-specific population East Europe, Black Sea & Mediterranean/Sub-Saharan Africa
RészletesebbenEladni könnyedén? Oracle Sales Cloud. Horváth Tünde Principal Sales Consultant 2014. március 23.
Eladni könnyedén? Oracle Sales Cloud Horváth Tünde Principal Sales Consultant 2014. március 23. Oracle Confidential Internal/Restricted/Highly Restricted Safe Harbor Statement The following is intended
RészletesebbenSupporting Information
Supporting Information Cell-free GFP simulations Cell-free simulations of degfp production were consistent with experimental measurements (Fig. S1). Dual emmission GFP was produced under a P70a promoter
RészletesebbenPIACI HIRDETMÉNY / MARKET NOTICE
PIACI HIRDETMÉNY / MARKET NOTICE HUPX DAM Másnapi Aukció / HUPX DAM Day-Ahead Auction Iktatási szám / Notice #: HUPX-MN-DAM-2018-0001 Dátum / Of: 26/01/2018 Tárgy / Subject: Hatályos díjszabás és kedvezmények
RészletesebbenHasznos és kártevő rovarok monitorozása innovatív szenzorokkal (LIFE13 ENV/HU/001092)
Hasznos és kártevő rovarok monitorozása innovatív szenzorokkal (LIFE13 ENV/HU/001092) www.zoolog.hu Dr. Dombos Miklós Tudományos főmunkatárs MTA ATK TAKI Innovative Real-time Monitoring and Pest control
RészletesebbenDR. BOROMISZA ZSOMBOR. A zalakarosi termáltó tájbaillesztése
DR. BOROMISZA ZSOMBOR A zalakarosi termáltó tájbaillesztése A zalakarosi Termáltó és Ökopart projekthez kapcsolódóan a tájépítészeti eszköztár szinte minden elemére szükség volt, hiszen védett növények
RészletesebbenFÖLDRAJZ ANGOL NYELVEN
Földrajz angol nyelven középszint 1311 ÉRETTSÉGI VIZSGA 2013. május 15. FÖLDRAJZ ANGOL NYELVEN KÖZÉPSZINTŰ ÍRÁSBELI ÉRETTSÉGI VIZSGA JAVÍTÁSI-ÉRTÉKELÉSI ÚTMUTATÓ EMBERI ERŐFORRÁSOK MINISZTÉRIUMA Paper
RészletesebbenMiskolci Egyetem Gazdaságtudományi Kar Üzleti Információgazdálkodási és Módszertani Intézet. Hypothesis Testing. Petra Petrovics.
Hypothesis Testing Petra Petrovics PhD Student Inference from the Sample to the Population Estimation Hypothesis Testing Estimation: how can we determine the value of an unknown parameter of a population
RészletesebbenUNIVERSITY OF PUBLIC SERVICE Doctoral School of Military Sciences. AUTHOR S SUMMARY (Thesis) Balázs Laufer
DOI azonosító: 10.17625/NKE.2013.021 UNIVERSITY OF PUBLIC SERVICE Doctoral School of Military Sciences AUTHOR S SUMMARY (Thesis) Balázs Laufer LAW ENFORCEMENT AND NATIONAL SECURITY CHALLENGES POSED BY
RészletesebbenBudapesti Műszaki és Gazdaságtudományi Egyetem Építőmérnöki Kar
M Ű E G Y E T E M 1 7 8 2 Budapesti Műszaki és Gazdaságtudományi Egyetem Építőmérnöki Kar AZ ÁGYAZATRAGASZTÁSI TECHNOLÓGIÁVAL STABILIZÁLT ZÚZOTTKŐ ÁGYAZATÚ VASÚTI FELÉPÍTMÉNY STATIKUS ÉS DINAMIKUS TERHEKRE
RészletesebbenAO-PPSCAD: The national monitoring plan includes the number of samplings for primary plant products: they already feature in the plan for 2012.
1 Ensure official controls of food contaminants across the whole food chain in order to monitor the compliance with the requirements of Regulation (EC) No 1881/2006 in all food establishments, including
RészletesebbenNéhány folyóiratkereső rendszer felsorolása és példa segítségével vázlatos bemutatása Sasvári Péter
Néhány folyóiratkereső rendszer felsorolása és példa segítségével vázlatos bemutatása Sasvári Péter DOI: http://doi.org/10.13140/rg.2.2.28994.22721 A tudományos közlemények írása minden szakma művelésének
RészletesebbenBird species status and trends reporting format for the period 2008-2012 (Annex 2)
1. Species Information 1.1 Member State Hungary 1.2.2 Natura 2000 code A129 1.3 Species name Otis tarda 1.3.1 Sub-specific population 1.4 Alternative species name 1.5 Common name túzok 1.6 Season Breeding
RészletesebbenAz EU szennyezésijog-piaca
Az EU szennyezésijog-piaca direktíva: 2002 dec. a kiotói átlagosan 8%-os csökkentés megvalósítására szolgál a CO 2 -kibocsájtási csökkentés kötelezettségének 46%-ára vonatkozik a legalább 1%-ot kibocsájtókra
RészletesebbenKönnyen bevezethető ITIL alapú megoldások a Novell ZENworks segítségével. Hargitai Zsolt Sales Support Manager Novell Hungary
Könnyen bevezethető ITIL alapú megoldások a Novell ZENworks segítségével Hargitai Zsolt Sales Support Manager Novell Hungary Napirend ITIL rövid áttekintés ITIL komponensek megvalósítása ZENworks segítségével
RészletesebbenMAKING MODERN LIVING POSSIBLE. Danfoss Heating Solutions
MAKING MODERN LIVING POSSIBLE Danfoss Danfoss Link Link HC Hidronikus HC Hydronic szabályozó Controller Szerelési Installation útmutató Guide Danfoss Heating Solutions Szerelési útmutató Tartalomjegyzék
RészletesebbenPerformance Modeling of Intelligent Car Parking Systems
Performance Modeling of Intelligent Car Parking Systems Károly Farkas Gábor Horváth András Mészáros Miklós Telek Technical University of Budapest, Hungary EPEW 2014, Florence, Italy Outline Intelligent
RészletesebbenÚJ ESZKÖZÖK A TÁJÖKOLÓGIAI ELVÛ TERVEZÉSBEN: TÁJÖKOLÓGIAI VIZUÁLIS PLANTÁCIÓ (TVP)
Tájökológiai Lapok 3 (2): 281 290. (2005) 281 ÚJ ESZKÖZÖK A TÁJÖKOLÓGIAI ELVÛ TERVEZÉSBEN: TÁJÖKOLÓGIAI VIZUÁLIS PLANTÁCIÓ (TVP) BARDÓCZYNÉ SZÉKELY EMÕKE 1, BARDÓCZY EMÕKE 2, BARCZI ATTILA 1, PENKSZA KÁROLY
RészletesebbenAgri- environment in the Rural Economy in Hungary Agnes Kaloczkai, Hungarian Academy of Sciences
Agri- environment in the Rural Economy in Hungary Agnes Kaloczkai, Hungarian Academy of Sciences kaloczkai.agnes@gmail.com Dr Eszter Kovacs, Department of Geography, University of Cambridge eszter.kovacs@geog.cam.ac.uk
RészletesebbenT/3402. számú. törvényjavaslat
MAGYARORSZÁG KORMÁNYA T/3402. számú törvényjavaslat a Magyarország Kormánya és a Koreai Köztársaság Kormánya között a vezetői engedélyek kölcsönös elismeréséről és cseréjéről szóló megállapodás kihirdetéséről
RészletesebbenKezdőlap > Termékek > Szabályozó rendszerek > EASYLAB és TCU-LON-II szabályozó rendszer LABCONTROL > Érzékelő rendszerek > Típus DS-TRD-01
Típus DS-TRD FOR EASYLAB FUME CUPBOARD CONTROLLERS Sash distance sensor for the variable, demand-based control of extract air flows in fume cupboards Sash distance measurement For fume cupboards with vertical
RészletesebbenA TÓGAZDASÁGI HALTERMELÉS SZERKEZETÉNEK ELEMZÉSE. SZATHMÁRI LÁSZLÓ d r.- TENK ANTAL dr. ÖSSZEFOGLALÁS
A TÓGAZDASÁGI HALTERMELÉS SZERKEZETÉNEK ELEMZÉSE SZATHMÁRI LÁSZLÓ d r.- TENK ANTAL dr. ÖSSZEFOGLALÁS A hazai tógazdasági haltermelés a 90-es évek közepén tapasztalt mélypontról elmozdult és az utóbbi három
RészletesebbenThe system of mobile tank fire-fighting equipment A mobil tartály tűzoltás technikai eszközrendszere
OLAJ- ÉS VEGYIPARI TŰZOLTÓSÁGOK 5. NEMZETKÖZI KONFERENCIÁJA 5 th INTERNATIONAL CONFERENCE FOR FIRE BRIGADES IN THE OIL & CHEMICAL INDUSTRY The system of mobile tank fire-fighting equipment A mobil tartály
RészletesebbenIntézményi IKI Gazdasági Nyelvi Vizsga
Intézményi IKI Gazdasági Nyelvi Vizsga Név:... Születési hely:... Születési dátum (év/hó/nap):... Nyelv: Angol Fok: Alapfok 1. Feladat: Olvasáskészséget mérő feladat 20 pont Olvassa el a szöveget és válaszoljon
Részletesebben24th October, 2005 Budapest, Hungary. With Equal Opportunities on the Labour Market
24th October, 2005 Budapest, Hungary Nemzeti és Etnikai Kisebbségi Jogok With Equal Opportunities on the Labour Market Equal Opportunities for the Roma Nemzeti és Etnikai Kisebbségi Jogok The government
RészletesebbenSzéchenyi István Egyetem www.sze.hu/~herno
Oldal: 1/6 A feladat során megismerkedünk a C# és a LabVIEW összekapcsolásának egy lehetőségével, pontosabban nagyon egyszerű C#- ban írt kódból fordítunk DLL-t, amit meghívunk LabVIEW-ból. Az eljárás
RészletesebbenHistory. Barcelona 11 June 2013 HLASA 1
History 1893 National Ornithological Centre (Ottó Herman) New ways of breeding and use of laboratory animals (Dr.Kállai László A laboratoriumiállat-tenyésztés és felhasználás új útjai. In: A biológia aktuális
RészletesebbenBevezetés a kvantum-informatikába és kommunikációba 2015/2016 tavasz
Bevezetés a kvantum-informatikába és kommunikációba 2015/2016 tavasz Kvantumkapuk, áramkörök 2016. március 3. A kvantummechanika posztulátumai (1-2) 1. Állapotleírás Zárt fizikai rendszer aktuális állapota
RészletesebbenMINO V2 ÁLLVÁNY CSERÉJE V4-RE
MINO V2 remote controlled MINO V2 ÁLLVÁNY CSERÉJE V4-RE Mino V3 circuit board replacement Mino V2-V4 csere készlet ezüst Art# 59348S, Mino V2-V4 csere készlet fehér Art# 59348W V4 áramköri lap Art# 75914
RészletesebbenA Magyar Honvédség hírrendszerének továbbfejlesztése
A Magyar Honvédség hírrendszerének továbbfejlesztése Pándi Balázs 1 A zártcélú távközlõ hálózatokról szóló hatályos jogszabályban megfogalmazottak alapján a Magyar Honvédség Hálózata 2 mentesített az Elektronikus
RészletesebbenRotary District 1911 DISTRICT TÁMOGATÁS IGÉNYLŐ LAP District Grants Application Form
1 A Future Vision pilot célja a Future Vision Plan (Jövőkép terv) egyszerűsített támogatási modelljének tesztelése, és a Rotaristák részvételének növelése a segélyezési folyamatokban. A teszt során a districteknek
RészletesebbenCharacteristics and categorization of transportation organizations
Characteristics and categorization of transportation organizations Organisational structure Activity (function) structure functional unit organisational unit sub-system input, stored, output information
RészletesebbenPIACI HIRDETMÉNY / MARKET NOTICE
PIACI HIRDETMÉNY / MARKET NOTICE HUPX DAM Másnapi Aukció / HUPX DAM Day-Ahead Auction Iktatási szám / Notice #: HUPX-MN-DAM-2018-0010 Dátum / Of: 12/10/2018 Tárgy / Subject: Hatályos díjszabás és kedvezmények
RészletesebbenReport on the main results of the surveillance under article 11 for annex II, IV and V species (Annex B)
0.1 Member State HU 0.2.1 Species code 4110 0.2.2 Species name Pulsatilla pratensis ssp. hungarica 0.2.3 Alternative species Pulsatilla flavescens scientific name 0.2.4 Common name magyar kökörcsin 1.
RészletesebbenFÖLDRAJZ ANGOL NYELVEN
Földrajz angol nyelven középszint 1112 ÉRETTSÉGI VIZSGA 2014. május 15. FÖLDRAJZ ANGOL NYELVEN KÖZÉPSZINTŰ ÍRÁSBELI ÉRETTSÉGI VIZSGA JAVÍTÁSI-ÉRTÉKELÉSI ÚTMUTATÓ EMBERI ERŐFORRÁSOK MINISZTÉRIUMA Paper
RészletesebbenDANS és Narcis. Burmeister Erzsébet. HUNOR találkozó, Budapest 2013. március 13.
DANS és Narcis Burmeister Erzsébet HUNOR találkozó, Budapest 2013. március 13. DANS DANS (Data Archiving and Network Services) http://www.dans.knaw.nl Kutatási adatok archiválása a saját fejlesztésű EASY
RészletesebbenLexington Public Schools 146 Maple Street Lexington, Massachusetts 02420
146 Maple Street Lexington, Massachusetts 02420 Surplus Printing Equipment For Sale Key Dates/Times: Item Date Time Location Release of Bid 10/23/2014 11:00 a.m. http://lps.lexingtonma.org (under Quick
RészletesebbenIII. Bajai Gabona Partnerség. III. Baja Grain Partnership
III. Bajai Gabona Partnerség Előadó:Nagy László, a Bajai OKK Kft. ügyvezetője 2011. Június 16. III. Baja Grain Partnership Presenter: László Nagy, managing director of Baja Public Port Ltd. 16th June,
RészletesebbenUtolsó frissítés / Last update: február Szerkesztő / Editor: Csatlós Árpádné
Utolsó frissítés / Last update: 2016. február Szerkesztő / Editor: Csatlós Árpádné TARTALOM / Contents BEVEZETŐ / Introduction... 2 FELNŐTT TAGBÉLYEGEK / Adult membership stamps... 3 IFJÚSÁGI TAGBÉLYEGEK
RészletesebbenBérczi László tű. dandártábornok Országos Tűzoltósági Főfelügyelő
The role of volunteer firefighter organizations, municipality and facility firefighter departments in the unified disaster management system of Hungary Bérczi László tű. dandártábornok Országos Tűzoltósági
RészletesebbenÁprilisban 14%-kal nőtt a szálláshelyek vendégforgalma Kereskedelmi szálláshelyek forgalma, 2014. április
Közzététel: 2014. június 10. Következik: 2014. június 11. Fogyasztói árak, 2014. május Sorszám: 77. Áprilisban 14%-kal nőtt a szálláshelyek vendégforgalma Kereskedelmi szálláshelyek forgalma, 2014. április
RészletesebbenCloud computing. Cloud computing. Dr. Bakonyi Péter.
Cloud computing Cloud computing Dr. Bakonyi Péter. 1/24/2011 1/24/2011 Cloud computing 2 Cloud definició A cloud vagy felhő egy platform vagy infrastruktúra Az alkalmazások és szolgáltatások végrehajtására
RészletesebbenENROLLMENT FORM / BEIRATKOZÁSI ADATLAP
ENROLLMENT FORM / BEIRATKOZÁSI ADATLAP CHILD S DATA / GYERMEK ADATAI PLEASE FILL IN THIS INFORMATION WITH DATA BASED ON OFFICIAL DOCUMENTS / KÉRJÜK, TÖLTSE KI A HIVATALOS DOKUMENTUMOKBAN SZEREPLŐ ADATOK
RészletesebbenAngol Középfokú Nyelvvizsgázók Bibliája: Nyelvtani összefoglalás, 30 kidolgozott szóbeli tétel, esszé és minta levelek + rendhagyó igék jelentéssel
Angol Középfokú Nyelvvizsgázók Bibliája: Nyelvtani összefoglalás, 30 kidolgozott szóbeli tétel, esszé és minta levelek + rendhagyó igék jelentéssel Timea Farkas Click here if your download doesn"t start
RészletesebbenMiddle Tisza District Environment and Water Directorate. Information tools of flood risk mapping
Middle Tisza District Environment and Water Directorate Information tools of flood risk mapping Presented by: László Kummer Aims Fulfilling the European Parlaiment s and Council s 2007/60/EC Directive
Részletesebben4-42 ELECTRONICS WX210 - WX240
4-42 ELECTRONICS WX210 - WX240 PCS 40000499-en Fig. 8 WX210 - WX240 ELECTRONICS 4-43 PCS COMPONENTS 40000471-en Load-limit regulator Legend Fig. 1 Fig. 2 1 Power supply 2 PWM1 output, proportional valve
RészletesebbenOn The Number Of Slim Semimodular Lattices
On The Number Of Slim Semimodular Lattices Gábor Czédli, Tamás Dékány, László Ozsvárt, Nóra Szakács, Balázs Udvari Bolyai Institute, University of Szeged Conference on Universal Algebra and Lattice Theory
RészletesebbenMadách Trade Center Bt. 1075 Budapest, Madách I. út 13-14. T (+36 1) 268 1900, (+36 1) 268 1901 F (+36 1) 269 6684 www.madachtrade.
Madách Trade Center Bt. 1075 Budapest, Madách I. út 13-14. T (+36 1) 268 1900, (+36 1) 268 1901 F (+36 1) 269 6684 www.madachtrade.hu info@madachtrade.hu bemutatkozás Bemutatkozás A Madách Trade Center
RészletesebbenCloud computing Dr. Bakonyi Péter.
Cloud computing Dr. Bakonyi Péter. 1/24/2011 Cloud computing 1/24/2011 Cloud computing 2 Cloud definició A cloud vagy felhő egy platform vagy infrastruktúra Az alkalmazások és szolgáltatások végrehajtására
RészletesebbenUtilizing Geothermal Energy in Hungary Today
Utilizing Geothermal Energy in Hungary Today International Workshop (Conference on Renewable Energy potentials is approaching (26-27 of March, 2015)) Dr. Habil Lajos Göőz Professor emeritus E-mail: goozl@upcmail.hu
RészletesebbenA TALAJTAKARÁS HATÁSA A TALAJ NEDVESSÉGTARTALMÁRA ASZÁLYOS IDŐJÁRÁSBAN GYÖNGYÖSÖN. VARGA ISTVÁN dr. - NAGY-KOVÁCS ERIKA - LEFLER PÉTER ÖSSZEFOGLALÁS
A TALAJTAKARÁS HATÁSA A TALAJ NEDVESSÉGTARTALMÁRA ASZÁLYOS IDŐJÁRÁSBAN GYÖNGYÖSÖN VARGA ISTVÁN dr. - NAGY-KOVÁCS ERIKA - LEFLER PÉTER ÖSSZEFOGLALÁS A globális felmelegedés kedvezőtlen hatásai a Mátraaljai
Részletesebben± ± ± ƒ ± ± ± ± ± ± ± ƒ. ± ± ƒ ± ± ± ± ƒ. ± ± ± ± ƒ
± ± ± ± ƒ ± ± ± ƒ ± ± ƒ ± ç å ± ƒ ± ± ± ± ± ± ± ± ± ± ± ƒ ± ± ± ä ± ± ± ± ƒ ± ± ± ± ƒ ± ± ± ± ƒ ± ± ± ± ƒ ± ± ± ± ± ± ± ± ± ± ± ± ± ± ƒ ± ± ± ± ± ƒ ± ± ± ± ƒ ± ± ± ƒ ± ± ƒ ± ± ± ± ± ± ± ± ± ± ± ± ± ±
RészletesebbenHALLGATÓI KÉRDŐÍV ÉS TESZT ÉRTÉKELÉSE
HALLGATÓI KÉRDŐÍV ÉS TESZT ÉRTÉKELÉSE EVALUATION OF STUDENT QUESTIONNAIRE AND TEST Daragó László, Dinyáné Szabó Marianna, Sára Zoltán, Jávor András Semmelweis Egyetem, Egészségügyi Informatikai Fejlesztő
RészletesebbenTELJESÍTMÉNYNYILATKOZAT. sz HU
TELJESÍTMÉNYNYILATKOZAT sz. 0005 HU 1. A terméktípus egyedi azonosító kódja: fis her EA II feszítődü el 2. Felhasználás célja(i): Termék Fé dü elek eto a törté ő felhasználásra agy terhelhetőség Re deltetésszerű
RészletesebbenDECLARATION OF PERFORMANCE No. GST REV 1.03 According to Construction Products Regulation EU No. 305/2011
DECLARATION OF PERFORMANCE No. According to Construction Products Regulation EU No. 305/2011 This declaration is available in the following languages: English Declaration of Performance Page 2-3 Hungarian
RészletesebbenA Continental Automotive Hungary beszállítói stratégiája Beszállítók kiválasztása és fejlesztése helyben és globálisan
A Continental Automotive Hungary beszállítói stratégiája Beszállítók kiválasztása és fejlesztése helyben és globálisan Business Unit Passive Safety & Sensorics Continental Corporation A Continental világszerte
RészletesebbenE L İ T E R J E S Z T É S
AZ ELİTERJESZTÉS SORSZÁMA: 201. MELLÉKLET : 1 db TÁRGY: Partnervárosi együttmőködés aláírása E L İ T E R J E S Z T É S SZEKSZÁRD MEGYEI JOGÚ VÁROS ÖNKORMÁNYZATA KÖZGYŐLÉSÉNEK 2013. június 27-i ÜLÉSÉRE
RészletesebbenPIACI HIRDETMÉNY / MARKET NOTICE
PIACI HIRDETMÉNY / MARKET NOTICE HUPX DAM Másnapi Aukció / HUPX DAM Day-Ahead Auction Iktatási szám / Notice #: Dátum / Of: 18/11/2014 HUPX-MN-DAM-2014-0023 Tárgy / Subject: Változások a HUPX másnapi piac
RészletesebbenDR. BOROMISZA ZSOMBOR. A Velencei-tóhoz kapcsolódó tájvédelmi szakértői tevékenység
DR. BOROMISZA ZSOMBOR A Velencei-tóhoz kapcsolódó tájvédelmi szakértői tevékenység A Velencei-tavi tájhoz kapcsolódó személyes kötődésem diplomaterv, tdk dolgozat, majd doktori disszertáció formájában
RészletesebbenGottsegen National Institute of Cardiology. Prof. A. JÁNOSI
Myocardial Infarction Registry Pilot Study Hungarian Myocardial Infarction Register Gottsegen National Institute of Cardiology Prof. A. JÁNOSI A https://ir.kardio.hu A Web based study with quality assurance
Részletesebben